“The project involved the design and construction of the Bovilla drinking water plant serving the city of Tirana and ancillary works. Specifically, the works carried out were:
– Steel DN 900 adduction pipeline from the dam to the drinking water plant for a length of 10,200 m
– Potable drinking water plant for a flow rate of 1,800 l/s articulated with an inlet and apportionment artifact, clariflocculation and filtration. Articulated sludge line with thickening, chemical sludge conditioning, dewatering. Plumbing and electrical connection works
– Tirana feed tank totaling 30,000 m3 complete with maneuvering chamber and DN 1200 piping
– Intake pipeline to the Tirana steel network DN 1200 for a total length of 1,700 m
– Interim management of the work for a period of thirteen months.”