FINAL AWARD OF ADJUSTMENT AND IMPROVEMENT OF THE PLANT IN GROTTAROSSA FOR THE POTABILIZATION OF THE WATER DERIVED BY TEVERE RIVER – CONTRACTING AUTHORITY ACEA ATO 2 S.P.A.

13/04/2018

With note on 13.04.2019, ACEA ATO 2 S.p.A. has communicated the final award to Giovanni Putignano & Figli S.r.l. of the works for adjustment and improvement of the potabilization plant of Grottarossa, for a total amount of € 6 339 855.27.

The Company has now 30 days to deliver the detail design of the works. Scheduled time for work completion are, instead, 100 days.